8-16 Section 8-4 - Keyboard Block
8-4-1-4 Removal Procedure (cont’d)
4.) Disconnect three connectors (6-8) from the HUB board. Refer to Figure 8-20.
5.) Disconnect two connectors (9-10). Refer to Figure 8-21.
6.) Carefully lift the Keyboard assy from the system.
7.) Perform the following functional tests. If all are successful, include the debrief script provided below.
8-4-1-5 Mounting Procedure
Install the new parts in the reverse order of removal.
Figure 8-20 Disconnect 3 connectors from the HUB
Figure 8-21 Disconnect two connectors
Table 8-8 Functional Tests
Service Manual
Section Functional Test / Diagnostic Test Debrief Script
Section 4-3-1
Power On/Boot Up
“Service Manual, Direction
2300000, Rev 1+, Section 8-4-1. Equipment
passed all required tests and is ready for use. “
Section 4-3-2
Power Off / Shutdown
Section 4-7-1
Main Keyboard Assy validation
Section 4-3-4
System B/M-Mode Checks
Section 4-3-5
System CFM and PWD Checks
Section 10-5-2
Functional Checks (See Also Chapter 4)
6
7
8
HUB Board
9
10

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE LOGIQ 5 and is the answer not in the manual?

GE LOGIQ 5 Specifications

General IconGeneral
BrandGE
ModelLOGIQ 5
CategoryMedical Equipment
LanguageEnglish

Related product manuals