3-5-1-3 Power Up Sequence
1.) The Start Up Screen will be shown on the Monitor display when the system is turned ON.
2.) Then Start Loader display will be shown on the Monitor display. Then the scanner is booted up
automatically.
NOTE: To enter the Maintenance Mode, select Maintenance button.
NOTE: Figure 8-4 displays when Service Dongle inserted in Rear Panel.
NOTE: Start is selected automatically when it time out.
3-5-2 Power Off/ Shutdown
NOTE: After turning off a system, wait at least ten seconds before turning it on again. The system may
not be able to boot if power is recycled too quickly.
3-5-2-1 Power Shutdown
1.) Press the ON/OFF
key at the front of the System for about two (2) seconds. Refer to Figure 3-14
on page 3-12 .
2.) Switch OFF the Main Circuit Breaker at the rear of the system Refer to Figure 3-13 on page 3-11 .
3.) Disconnect the Main Power Cable is necessary. For example : Relocating the scanner.
Figure 3-16 Start Application Window
NOTICE
Disconnecting the Mains Power Cable before switching OFF the Circuit Breaker will activate the
uninterruptible power system (UPS) in the backend processor, forcing an ordered shutdown of the
system.
NOTICE
The UPS serves only as a battery backup that allows for a soft shut-down of the scanner to prevent file
corruption. IT DOES NOT REGULATE INCOMING VOLTAGE.