8-6-3-4 Removal Procedure (cont’d)
7.) Perform the following functional tests. If all are successful, include the debrief script provided below.
8-6-3-5 Mounting procedure
Install the new parts in the reverse order of removal.
Table 8-38 Functional Tests
Service Manual
Section Functional Test / Diagnostic Test Debrief Script
Section 4-3-1
Power On/Boot Up
“Service Manual, Direction
2300000, Rev 1+, Section 8-6-3. Equipment
passed all required tests and is ready for use. “
Section 4-3-2
Power Off / Shutdown
Section 4-8-2-4
Gas Spring Assy
Section 10-5-5
Physical Inspection