4 Operating Guide
4.1 Startup
Step 1: Connect Main Supply and Gas Supply
Plug the power cord into the AC power outlet and connect the pipeline gas supply and standby gas
supply. Turn on the cylinder valve of the standby gas supply and turn off the flowmeters of O
2
, N
2
O,
Air, and Aux. O
2
.
Step 2: Turn on the Power Switch
Turn the Power Switch to “ON”. The UI will power on and perform a System Self Test.
4.1.1 System Self Test
When the UI is powered on, the startup interface is displayed, followed by the LOGO interface.
Figure 4-1 LOGO Interface
The System Self Test interface will appear after the LOGO interface.
Figure 4-2 System Self Test Interface