Procedure
1. Power down the server.
2. Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
3. Do one of the following:
• Extend the server from the rack.
• Remove the server from the rack.
4. Remove the access panel.
5. Do one of the following:
• Remove the air baffle.
• If installed, remove the 4LFF midplane drive cage.
6. Do one of the following:
• For Type-a Smart Array controllers, install the controller into the Smart Array connector.
• For Type-p Smart Array controllers, install the controller into an expansion slot.
7. Cable the controller.
The installation is complete.