Figure 12-44 Installing the monitoring signal cable in the scenario of 1 RFC+1 APM30H+2
IBBS200Ds/IBBS200Ts (2)
Step 3 Attach labels to the installed cables. For details, see Attaching an L-Shaped Label.
Step 4 Run each cable that leave the cabinet in a PVC corrugated pipe, and then tie the pipe to the cable
hole in the cabinet.
Step 5 If two RFCs, two APM30Hs, and four IBBS200Ds/IBBS200Ts are configured on site, four more
monitoring signal cables are required. Figure 12-45 shows the configurations of the cabinets.
Figure 12-45 Configurations of two RFCs, two APM30Hs, and four IBBS200Ds/IBBS200Ts
BTS3900A(Ver.B)
Installation Guide 12 Installing the Cables