EasyManuals Logo

Huawei BTS3900A Installation Guide

Huawei BTS3900A
168 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #46 background imageLoading...
Page #46 background image
8 Installing the Base
This section describes the procedure and precautions for installing a base on the concrete floor.
Procedure
Step 1 Pour a concrete pad.
NOTE
l The height of the concrete pad must meet the heat dissipation and waterproofing requirements of the cabinet.
l The concrete pad must be at least 200 mm above the floor.
l The horizontal error of the poured concrete pad must be less than 5 mm.
Step 2 Align the base.
1. Determine the position for installing the cabinet according to the engineering design and
3.3 Installation Clearance Requirements for the BTS3900A.
2. On the concrete pad, mark holes to determine the installation position of the base, as shown
in Figure 8-1.
BTS3900A(Ver.B)
Installation Guide 8 Installing the Base
Issue 01 (2011-10-25) Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
37

Table of Contents

Other manuals for Huawei BTS3900A

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei BTS3900A and is the answer not in the manual?

Huawei BTS3900A Specifications

General IconGeneral
BrandHuawei
ModelBTS3900A
CategoryAccessories
LanguageEnglish

Related product manuals