13 Installation Checklist
After the cabinets and devices are all installed, you need to check the installation items,
installation environment, and cable-related items.
Checking the Cabinet Installation
Table 13-1 describes the cabinet installation checklist.
Table 13-1 Cabinet installation checklist
No.
Item
1 The installation position of the cabinet strictly complies with the engineering
design.
2 The base is securely installed.
3 All the bolts, especially those for electrical connections, are tightened. Both the
spring washer and the flat washer are installed in a correct sequence.
4 The cabinet is neat and clean.
5 The paint on the surface is satisfactory. The damaged paint is repaired. For details,
see 15.2 Applying Touch-Up Paint.
6 All labels, tags, and nameplates are correct, legible, and complete.
Installation Environment Checklist
Table 13-2 describes the installation environment checklist.
Table 13-2 Installation environment checklist
No.
Item
1 No redundant tapes or cable ties are left on the cables.
2 No tapes, tails of cable ties, paper, or packing bags are left around the cabinet.
BTS3900A(Ver.B)
Installation Guide 13 Installation Checklist
Issue 01 (2011-10-25) Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
150

Table of Contents

Other manuals for Huawei BTS3900A

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei BTS3900A and is the answer not in the manual?

Huawei BTS3900A Specifications

General IconGeneral
BrandHuawei
ModelBTS3900A
CategoryAccessories
LanguageEnglish

Related product manuals