13 Installation Checklist
After the cabinets and devices are all installed, you need to check the installation items,
installation environment, and cable-related items.
Checking the Cabinet Installation
Table 13-1 describes the cabinet installation checklist.
Table 13-1 Cabinet installation checklist
No.
Item
1 The installation position of the cabinet strictly complies with the engineering
design.
2 The base is securely installed.
3 All the bolts, especially those for electrical connections, are tightened. Both the
spring washer and the flat washer are installed in a correct sequence.
4 The cabinet is neat and clean.
5 The paint on the surface is satisfactory. The damaged paint is repaired. For details,
see 15.2 Applying Touch-Up Paint.
6 All labels, tags, and nameplates are correct, legible, and complete.
Installation Environment Checklist
Table 13-2 describes the installation environment checklist.
Table 13-2 Installation environment checklist
No.
Item
1 No redundant tapes or cable ties are left on the cables.
2 No tapes, tails of cable ties, paper, or packing bags are left around the cabinet.