Figure 7-20 Installing monitoring communications cables
----End
7.9.4 Installing AC Output Power Cables in a Parallel System
● Install short-circuit plates for AC output circuit breakers.
● The three cables from the AC output circuit breaker to the power modules must
be of the same length.
Procedure
Step 1 Install AC output power cables of the parallel box.
iSitePower-M (MAP05A1, MAB05B1)
User Manual 7 Electrical Connection
Issue 02 (2021-12-30) Copyright © Huawei Digital Power Technologies Co., Ltd. 75