Figure 7-6 Installing ground cables (capacity expansion scenario)
● In capacity expansion scenarios, bottom cascading cables must be routed from
the rear of the product.
● Cables outside the device must be routed through cable pipes.
----End
7.3 Installing AC Power Cables
● Do not reversely connect or short-circuit the live wire and neutral wire of an AC
power cable.
● The PE wire of an AC power cable must be grounded.
● Do not reversely connect AC input and output power cables.