Step 3 Route the cables out of the cable holes.
NO TICE
The outlet positions shown in the gure are for reference only. Select an
appropriate cable outlet based on the actual cable thickness.
Figure 7-25 Cable routes
Step 4 Tighten the screws.
Figure 7-26 Installing the decorative covers
----End
iSitePower-M (MAP05A1, MAB05B1)
User Manual 7 Electrical Connection
Issue 02 (2021-12-30) Copyright © Huawei Digital Power Technologies Co., Ltd. 80