Commissioning
Chapter 2 OPERATION MANUAL
V1.3.0en/06.07.15//14.06 Liability for errors and misprints excluded. CC®
27
Note the volume displacement caused by a sample (e.g. Erlenmeyer flask). Place your sample into
the empty bath. Only then fill in a sufficient amount of temperature control medium. Also note that
the level of the temperature control medium drops when you remove the sample. This may cause a
safety shutdown (low level protection) during an enabled thermoregulation. Therefore, switch off
the temperature control unit beforehand.
The entire area/volume of the “bath vessel Variostat” is not available (see picture above) in the
combination Variostat with “bath vessel Variostat”. For bath thermostats: Please note the size of the
bath opening (see data sheet from page 83 in section »Annex«.
2.9 Preparations for operation
2.9.1 Opening/closing valves
Opening valves:
Open valves by turning them counterclockwise (turn 90° left as far as it will go).
Close valves:
close valves by turning them clockwise (turn 90° right as far as it will go).
PROCEDURE
Check that all valves are closed.
Close all valves by turning them clockwise (turn 90° right as far as it will go).
2.9.2 Cooling/heating baths: Connect the energizing lead
Opening and closing
valves
Connect the energizing
lead K6