Commissioning
Chapter 2 OPERATION MANUAL
V1.3.0en/06.07.15//14.06 Liability for errors and misprints excluded. CC®
31
PROCEDURE
Connection of the cooling bath and the hanger thermostat with ONE power supply (only valid for
230 V version)
Connect the >power supply< [35] on the hanger thermostat with the >power supply< [65] on
the cooling bath. The cable required is included.
Connect the >power supply< [35] on the cooling bath with the building’s power supply. The
cable required is included.
2.11.4 Cooling/heating baths: Power cable connection of the K1x and K2x
2.11.4.1 Utilization as a pure cooling bath (without hanger thermostat)
PROCEDURE
Connect the cooling bath to the power supplies (valid for 100 V, 115 V and 230 V versions)
Connect the >power supply< [35] on the cooling bath with the building’s power supply. The
cable required is included.
Installing the power
cable connection (K6) -
one power supply
from the building (only
valid for 230 V version)
Installing the power
cable connection (K1x
+ K2x) - pure cooling
bath (valid for 100 V,
115 V and 230 V
versions)