Commissioning
Chapter 2 OPERATION MANUAL
V1.3.0en/06.07.15//14.06 Liability for errors and misprints excluded. CC®
PROCEDURE
Connection of the cooling bath and the hanger thermostat with ONE power supply (only valid for
230 V version)
Connect the >power supply< [35] on the hanger thermostat with the >power supply< [65] on
the cooling bath. The cable required is included.
Connect the >power supply< [35] on the cooling bath with the building’s power supply. The
cable required is included.
Installing the power
cable connection (K1x
+ K2x), cooling/heating
bath (only valid for
230 V version)