Commissioning
Initial switch−on
6
129
EDBMB9340 DE/EN/FR 12.0
6 Commissioning
6.1 Initial switch−on
Stop!
ƒ Prior to initial switch−on check the completeness, polarity, short circuit and
earth fault of the drive system wiring.
ƒ Keep to the switch−on sequence!
1. If 935x brake choppers are integrated into the drive system:
Ensure the mains supply is switched−off.
Use switches S1 and S2 to adapt the 935x brake chopper to the mains voltage (see
documentation for the brake chopper).
2. Switch on the mains.
The drive system will be ready for operation after approx. 0.5 s.
3. Control the readiness for operation via both LEDs at the front of the regenerative
power supply module:
Status Description
green red
on off l The regenerative power supply module is connected to the mains voltage and is ready for
operation.
l No faults.
off on Active fault
off off l Mains voltage is switched off
l Mains phase L2 or L3 failed
4. Adapt all controllers which are connected to the drive system to the mains voltage
(under C0173).