Manitowoc Published 03-29-17, Control # 064-23 v2 4-45
14000 OPERATOR MANUAL SETUP AND INSTALLATION
4
4. Continue to lower boom onto blocking until boom straps
are resting in brackets on boom inserts OR, if equipped
with intermediate suspension, proceed as follows:
See Figure 4-35
for the following steps.
a. Stop lowering boom once it is resting on blocking.
b. Boom up or down as required so pins (10, View G)
as loose.
c. Remove pins (10).
d. Boom down until lower strut (1a) is resting on pins
(8, View D).
e. Store pins (10, View D) in each end of bottom strut
(1a).
f. Boom up or down as required so pins (9, View F)
are loose.
g. Remove pins (9).
h. Boom down until upper strut (1a) is fully lowered to
shipping position and install pins (9, View D).
i. Continue to boom down until straps (4, View E) and
strap links (7) are resting on boom sections.
5. Disconnect load lines from load block and weight ball
and spool load lines onto load drums.