14000 OPERATOR MANUAL SETUP AND INSTALLATION
4
Install Block-Up Limit Control and Connect Boom
Wiring
Install block-up limit components as shown in Figure 4-38
and in Boom Wiring and Limits Electrical Drawing at end of
this section.
Connect plugs from electric cables to corresponding
receptacles (see Figure 4-39
).
• To prevent dirt and moisture from entering electric
components, connect dust caps (1) to all unused plugs,
terminating plugs, and receptacles
• Connect terminating plugs (SP) to unused plugs. Failing
to perform this step will cause a fault alert and
corresponding function will not operate properly
• Install wind speed indicator assembly if removed for
shipping. Use star washers to attach mounting bracket
to boom top to provide a good ground (see Wind Speed
Assembly drawing at end of this section)
• Connect electrical cable at base of wind speed mounting
bracket

Table of Contents

Other manuals for Manitowoc 14000

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc 14000 and is the answer not in the manual?

Manitowoc 14000 Specifications

General IconGeneral
BrandManitowoc
Model14000
CategoryConstruction Equipment
LanguageEnglish

Related product manuals