Install the Boom Load Lines
1. Route the load lines up the boom. See Figure 4-114 on
page 4-170.
2. Pull the load lines approximately 20 ft (6,1 m) past the
end of the boom.
3. Install the load block(s) and hook-and-weight ball after
the boom is raised to a convenient height. See Boom
Raising Procedure on Boom Raising Procedure on
page 4-110.
If equipped, the rigging winch can be used to assist in
pulling the load lines. See Rigging Winch Operation on
page 4-168.
4. Read the following topics:
Wire Rope Installation on page 4-161
Load Line Reeving on page 4-171
Wire Rope Specifications on page 4-171
Reeving diagrams at the end of this section
Install Boom Block-Up Limit Components
Install the block-up limit components as shown in
Figure 4-73
.
The chain and weight for the lower boom point are
stored on brackets in the boom top.
The chain and weight for the upper boom point are
stored on brackets on the upper boom top.