Assembly, Erection and Stripping
General
The following assembly, erection,
and stripping information is
provided as a guide, and is not
intended to be all-inclusive. The
contractor is responsible for
the safe usage of the formwork
equipment in accordance with all
applicable government regulations,
codes, and ordinances. Refer to the
appropriate sections of this manual
for more detailed information on
the components described.
Unloading and Assembly
When unloading panels from
the truck or moving them on the
jobsite, appropriate crane slings
and lifting equipment should be
used.
For gang forming:
1. The assembly area should
be clean, level, and capable of
supporting the expected load.
2. Arrange panels face down as
needed for the gang (Fig.50.1).
3. Install the assembly locks,
steel rails, bracing, and walkway
brackets (Fig.50.2).
Fig. 50.1
Fig. 50.2
Wall formwork