FMON10JEN 07.04.2017 Rev. 10J
13 (13)
All components used must be suitable for use in:
– the system’s maximum operating pressure, and
– the system’s minimum and maximum ambient temperature range.
No parts of the centralised lubrication system may be subjected to twisting, shearing, or bending.
Before using any parts, check them for contamination; clean if necessary.
Lubricant lines should be primed with lubricant prior to installation. This makes it easier to bleed the
system of air afterwards.
Observe the specified tightening torques. Use a calibrated torque wrench.
When working with heavy parts, use suitable lifting tools.
Avoid mixing up dismantled parts or assembling parts in the wrong order by marking the parts accord-
ingly.
Commissioning and daily start-up
Ensure that:
All safety devices are completely installed and work properly.
All connections are correctly connected.
All parts have been correctly installed.
All warning labels on the machine are complete, highly visible and undamaged.
Replace illegible or missing warning labels without delay.
Cleaning
There is a risk of fire and explosion when using flammable cleaning agents. Use only non-flammable
cleaning agents suitable for the purpose.
Do not use aggressive cleaning agents.
Do not clean using a steam jet or pressure washer, as these may damage electrical components.
Observe the IP protection class.
Cleaning work on energised components may be carried out by electrical specialists only.
Mark damp areas accordingly.