5.5 Transport and Shipping
5.5.1 Attentions
• The PCS should be transported and installed as an integrated unit. Failure
caused by unauthorized disassembly is not covered by warranty.
• Transport the PCS strictly following the description in this chapter.
• Always keep in mind the non-central center of gravity of the PCS and gravity
mark on the PCS.
• Please take the heavy weight of the PCS into consideration during shipping and
moving.
• Always keep the PCS upright!
• Inclination angle <5˚. If the inclination angle is more than 5˚, PCS may tip over.
Due to the large volume and weight of the PCS, it is easy to cause casualties
and device damage once it is dumped.
• Avoid sudden force when moving or transporting the device.
Do not transport the PCS in rainy days or other harsh weather.
Take proper protective methods if the PCS must be transported in harsh days.
Only qualified personnel with professional authorization can transport and move
the PCS.
Please take necessary auxiliary methods to transport the PCS to the final installa-
tion place safely.
5.5.2 Moving the PCS
DC and AC cables are thick. For easy cable wiring and cable protection, lay the
DC and AC cables before moving the PCS to the final installation place.