Unpack the PCS only when it is to be installed. The PCS that has been unpacked can be
transported by forklift, crane, slide rails, etc.
Additional traction may be required if the PCS needs to be transported on slopes.
Slow down and be careful when moving the PCS on a slope to prevent it from slid-
ing down the forks and hitting the forklift.
Remove all obstacles that exist or may exist on the way, such as tree branches, cables, etc.
The PCS should be transported and moved under good weather conditions.
Be sure to set up warning signs or warning area to prevent non-staff from entering the lifting
area to avoid accidents.
In addition, before placing the PCS, ensure that:
The position where the PCS is placed should be solid and flat, well drained, free of obstacles
and protrusions. The PCS should be supported by only four bottom corner fittings.
• Forklift
Safety Operation Rules of forklift should be observed at all times.
When lift, move and put down the PCS with a forklift, make sure to be slow and
steady. The PCS can only be placed on a firm and stable ground.
When transporting the PCS with the wooden sealing boards, please insert the prongs in-
to the gap at the lower part of the boards, and then move the device. When transporting
the PCS without the sealing boards, ensure the center of gravity of the PCS is at the mid-
dle of the two prongs and then move the device.
figure 5-5 Move the PCS by forklift
*The figure above is indicative only.
table 5-1 Dimensions of Product with Sealing Boards
Width Height Depth
1750mm 2480mm 1450mm