TB7100 Installation and Operation Manual Preparation for Operation 103
© Tait Electronics Limited December 2005
7.6.2 Applying Power
Before turning on the base station, check that:
all looms and cables at the front and rear of the base station are fitted
correctly
all connectors are secure
the 20A fuse is fitted.
Turn on the power supply and check that the base station powers up
correctly:
The power LED on the user interface lights up.
The LCD indicates the current channel number.
7.6.3 Programming
Please see the line-controlled base “Programming” on page 82 for details on
how to program the base station for RF modem operation.
7.6.4 Audio Level Adjustment
In this configuration the system interface connector is not used, so it is not
necessary to set the line level or line Sensitivity.
Figure 7.9 System interface link positions
J400J500 J502J503 J501J221

Table of Contents

Other manuals for Tait TB7100

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Tait TB7100 and is the answer not in the manual?

Tait TB7100 Specifications

General IconGeneral
BrandTait
ModelTB7100
CategoryAccessories
LanguageEnglish

Related product manuals