(3) INSTALLATION
REASSEMBLY IN REVERSE ORDER OF
REMOVAL.
1) Install the engine on the front axle bracket.
2) Retightening the right hand pivot metal tightening
bolts.
3) Connect hoses.
4) Assemble the engine and the front transmission.
Note:
- Apply small mount of grease to each of the sliding
parts. Be careful not to apply excessive amount of
grease as this could cause clutch slipping.
- During operation, be sure to avoid any of the
reassembly operations that may place load upon the
input gear.
5) Install the hydraulic system piping.
6) Install the dash panel.
2-11
7) Install the wiring and rods.
8) Install the covers.
9) Connect the panel set wiring and then install the
panel.
10) Connect the wiring for the engine.
11) Connect the battery terminals.
12) Install the engine hood and side cover.
13) Remove the clutch housing and engine tightening
bolts and move the engine forward.