Assemble Tractor Sections.
NOTE:Splines on all drive shafts and couplers
must be aligned before tractor sections
are bolted together.
1.Align splines on hydrostatic transmission drive
shaft and engine fly wheel.
2.Move tractor sections together and retain with
5 screws.Tighten bolts to 90-110N.m.
3.Remove screws retaining splitting stands to
tractor sections.Remove splitting stands.
NOTE: Tractor shown split for clarity.
6.Connect suction tube to manifold.Tighten hose
clamp
7. Connect two hydrostatic charge pressure tubes
to hydrostatic transmission.Tighten to 40-57N.m
(30-43lb-ft).Check opposite ends of both tubes to
make sure they are tight.
8. Install a new hydraulic oil filter
4.Install rod as an assembly.Attach turn buckle
to hydrostatic control linkage and retain with
nut.
5.Connect switch connector
9. Install 4WD drive shaft and couplers. Slide
couplers onto shafts,and retain with snap ring
4-21