Vertiv | NetSure 7100 Series -48V DC Power System Installation Manual (IM582127000) | Rev. BB
24
Placing the Enclosures, Bolting Enclosures Together, and Securing the Enclosure(s) to the
Floor (if applicable)
System components are factory mounted in a relay rack, on shipping rails, or in an enclosure as specified when
ordered.
Systems Installed in an Enclosure
The system consists of one to six bays. Locate enclosures in a line adjacent to each other, with no space
between them. Place the List 1 Main Bay at the right or left side end, then the List 7 Supplemental Bay, then the
List 8 Supplemental Bay (if furnished), etc. Refer to the following procedures.
Ventilation Requirements
Refer to the General Requirements” on page 16.
Enclosure Floor Mounting Dimensions
Refer to Figure 5 for enclosure floor mounting dimensions.
Figure 5:
Enclosure Floor Mounting Dimensions

Table of Contents

Other manuals for Vertiv NetSure 7100 Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Vertiv NetSure 7100 Series and is the answer not in the manual?

Vertiv NetSure 7100 Series Specifications

General IconGeneral
BrandVertiv
ModelNetSure 7100 Series
CategoryPower Supply
LanguageEnglish

Related product manuals