LTN Appendix IV—CE Pallet Assembly
wc_tx001215gb.fm 79
12 Appendix IV—CE Pallet Assembly
Overview
This set of assembly instructions applies to CE machines shipped on a pallet as
shown below. A palletized CE machine is intended to be mounted on a trailer that
meets local regulations. This Manual does not include instructions for mounting a
palletized CE machine on a trailer.
If your machine does not look like the one shown in the illustration, refer to Machine
Identification in the Introduction chapter to identify the appropriate set of assembly
instructions.
Tasks
To complete the assembly of your Light Tower, the following tasks must be
performed in the order listed:
Tools and
materials
The following tools and materials are needed:
Appropriate machine lifting gear
Basic hand tools (wrenches, screwdrivers, etc.)
wc_gr006468
Task Description See topic
Lift the machine
1 Lift the machine using appropriate lifting gear
Install the jacks
2 Install the side jacks 12.1
3 Install the rear jack 12.2