SPEEDGATE Installation and Maintenance Manual Revision 1 - MAY 2023
49
SPEEDGATE INSTALLATION
Gate Installaon
Use extreme cauon when handling, moving, or slinging the panel secons. Black
gate edges may be installed (one horizontal on boom of outer panel secon, two
vercal on inner panel secon). They are suscepble to damage if mishandled.
Always use blocking when working with panels to prevent damage to gate edges.
1. Using slings and/or appropriate straps, secure a strap onto the liing assembly that is provided with
the gates. Once secure, begin liing unl strap is taut but not liing the gate. The gate can now be
unbolted from the shipping skid. Once all bolts are unfastened raise the gate up and place onto the
concrete anchors in the concrete foundaon.
Figure 9. Gate and Liing Assembly