Appendix
Wieland Electric GmbH | BA000966 | 07/2016 (Rev. C)
Checklist for manufacturers
888586251
The information in the following points must be available at least during first-time commission-
ing. It may vary depending on the application and the requirements from the manufactu-
rer/supplier must be checked.
This checklist should be retained or stored with the machine documents so that it can be used
as a reference during recurring tests.
This checklist is not a replacement for the first-time commissioning or the regular testing
done by a qualified person.
Table 52: Checklist for first-time commissioning
Were the safety guidelines according to the directives/standards valid
for the machine used as a basis?
o
o
Are the directives and standards used listed in the Declaration of Con-
o
o
Does the safety equipment correspond to the required category?
Are the required protective measures against electric shock effective
o
o
Has the protective function been checked in accordance with the
testing information in this documentation? In particular:
• Functional check of the command devices, sensors, and actuators
connected to the safety control
• Test of all switch-off paths
o
o
Have you ensured that a complete test of the safety functions has
been carried out after every configuration change to the safety con-
o
o