<7. System Delivery Precautions>
7.2.3 System Delivery
1. If delivering equipment used in user acceptance test as is
No special delivery engineering is required except for pre-delivery preparation and
control application backup.
2. If delivering FCN-500, FCN-RTU CPU module and PC
Same as case 1, for this case where the FCN-500 or FCN-RTU was delivered early
and only the CPU module and PC are to be delivered after UAT, no special delivery
engineering is required except for pre-delivery preparation and control application
backup.
In addition, prepare a procedure instruction sheet for checking Resource
Configurator configuration information for the site system and redefining the
configuration accordingly as this work need to be done on-site.
3. If delivering only the FCN-500, FCN-RTU CPU module
Same as cases 1 and 2 above, for this case where the FCN-500 or FCN-RTU and
PC were delivered early and only the CPU module is to be delivered, no CPU
module related delivery engineering is required except for system card backup.
In addition, prepare a procedure instruction sheet for decompressing the delivered
zwt format backup file and restoring the Logic Designer control application on the
site PC as this work needs to be done on-site.