EasyManuals Logo

ABB RET670 Commissioning Manual

ABB RET670
328 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #230 background imageLoading...
Page #230 background image
1. Check that the IED settings are appropriate, for example the PUFrequency, VMin,
and the tDelay.
2. Supply the IED with three-phase voltages at rated values.
3. Slowly decrease the magnitude of the applied voltage, until the BLKDMAGN signal
appears.
4. Note the voltage magnitude value and compare it with the set value VMin.
5. Slowly decrease the frequency of the applied voltage, to a value below
PUFrequency.
6. Check that the PICKUP signal does not appear.
7. Wait for a time corresponding to tDelay, make sure that the TRIP signal does not
appear.
11.7.1.2 Completing the test
Continue to test another function or end the test by changing the TESTMODE setting to
Disabled. Restore connections and settings to their original values, if they were changed
for testing purposes.
11.7.2 Overfrequency protection SAPTOF (81)
Prepare the IED for verification of settings outlined in Section
"Preparing the IED to
verify settings".
11.7.2.1 Verifying the settings
Verification of PICKUP value and time delay to trip
1. Check that the IED settings are appropriate, for example the pickup value and the
time delay.
2. Supply the IED with three-phase voltages at their rated values and initial frequency.
3. Slowly increase the frequency of the applied voltage with a 40 mHz step, applying
it for a period that is 10% longer than tDelay.
4. Note the trip value and compare it with the set value.
5. Decrease the frequency to rated operating conditions.
6. Check that the PICKUP signal resets.
7. Set the frequency to 20 mHz under the trip value.
8. Increase the frequency with a 40 mHz step, applying it for a period that is 10% longer
than tDelay.
9. Measure the time delay for the TRIP signal, and compare it with the set value. Note
that the measured time consists of the set value for time delay plus minimum trip
time of the pickup function (80 - 90 ms).
Section 11 1MRK 504 165-UUS -
Testing functionality by secondary injection
224 Transformer protection RET670 2.2 ANSI
Commissioning manual

Table of Contents

Other manuals for ABB RET670

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB RET670 and is the answer not in the manual?

ABB RET670 Specifications

General IconGeneral
Rated Frequency50/60 Hz
InputsAnalog and binary inputs
ApplicationProtection of power systems
Communication ProtocolsIEC 61850, DNP3, Modbus
Operating Temperature Range-25°C to +55°C
MountingRack mounted
Number of Binary InputsUp to 48
Number of Binary Outputs32
Protection FunctionsOvercurrent Protection
OutputsBinary outputs
EnclosureIP 54
TypeLine Differential Protection
Number of Analog Inputs24

Related product manuals