EasyManuals Logo

ABB RET670 Commissioning Manual

ABB RET670
328 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #269 background imageLoading...
Page #269 background image
7. Apply a fault condition in the forward directed zone used for scheme communication
tripping.
8. Check that the no trip from scheme communication occurs.
9. Check that the trip time from the forward directed zone used for scheme
communication tripping complies with the zone timer and that correct trip outputs,
external signals, and indications are obtained for the actual type of fault generated.
11.11.2.4 Completing the test
Continue to test another function or end the test by changing the TESTMODE setting to
Disabled. Restore connections and settings to their original values, if they were changed
for testing purposes.
11.11.3 Current reversal and Weak-end infeed logic for distance
protection 3-phase ZCRWPSCH (85)
Prepare the IED for verification of settings outlined in Section "Preparing the IED to
verify settings".
Values of the logical signals for ZCRWPSCH are available on the local HMI under Main
menu/Tests/Function status / Scheme communication / ZCRWPSCH(85) /ZCRWPSCH:
1.
The Signal Monitoring in PCM600 shows signals that are available on the Local HMI.
The current reversal logic and the weak-end infeed functions are tested during the
secondary-injection test of the impedance or overcurrent protection zones together with
the scheme communication logic for the distance protection function ZCPSCH (85).
11.11.3.1 Current reversal logic
It is possible to check the delay of the CS send signal with tDelayRev by changing from
a reverse to a forward fault.
By continuously activating the CR input and changing from a reverse to a forward fault,
the delay tDelayRev can be checked.
Checking of current reversal
The reverse zone timer must not operate before the forward zone fault is
applied. The user might need to block the reverse zone timer setting during
testing of current reversal.
1MRK 504 165-UUS - Section 11
Testing functionality by secondary injection
Transformer protection RET670 2.2 ANSI 263
Commissioning manual

Table of Contents

Other manuals for ABB RET670

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB RET670 and is the answer not in the manual?

ABB RET670 Specifications

General IconGeneral
Rated Frequency50/60 Hz
InputsAnalog and binary inputs
ApplicationProtection of power systems
Communication ProtocolsIEC 61850, DNP3, Modbus
Operating Temperature Range-25°C to +55°C
MountingRack mounted
Number of Binary InputsUp to 48
Number of Binary Outputs32
Protection FunctionsOvercurrent Protection
OutputsBinary outputs
EnclosureIP 54
TypeLine Differential Protection
Number of Analog Inputs24

Related product manuals