1. Deactivate the receive (CR) signal of the IED.
2. Apply healthy normal load conditions to the IED for at least two seconds.
3. Apply a fault condition within the forward directed zone used for scheme
communication tripping.
4. Check that correct trip outputs and external signals are obtained for the type of fault
generated and that the trip time complies with the tCoord timer (plus relay
measuring time).
5. Check that the other zones trip according to their zone times and that a send (CS)
signal is only obtained for the reverse zone.
6. Activate the IED receive (CR) signal.
7. Apply a fault condition in the forward directed zone used for scheme communication
tripping.
8. Check that the no trip from scheme communication occurs.
9. Check that the trip time from the forward directed zone used for scheme
communication tripping complies with the zone timer and that correct trip outputs,
external signals, and indications are obtained for the actual type of fault generated.
11.11.1.4 Testing delta blocking scheme
1. Deactivate the receive (CR) signal of the IED.
2. Apply healthy normal load conditions to the IED for at least two seconds.
3. Apply a fault condition within the forward directed zone used for scheme
communication tripping.
4. Check that correct trip outputs and external signals are obtained for the type of fault
generated and that the trip time complies with the tCoord timer (plus relay
measuring time).
5. Check that the other zones trip according to their zone times and that a send (CS)
signal is only obtained for the reverse zone.
6. Check that for a forward fault, carrier send (CS) signal is first obtained from the delta
based fault inception detection (as it is not directional) , and immediately inhibited
by the forward zone.
7. Activate the IED receive (CR) signal.
8. Apply a fault condition in the forward directed zone used for scheme communication
tripping.
9. Check that the no trip from scheme communication occurs.
10. Check that the trip time from the forward directed zone used for scheme
communication tripping complies with the zone timer and that correct trip outputs,
external signals, and indications are obtained for the actual type of fault generated.
Section 11 1MRK 504 165-UUS -
Testing functionality by secondary injection
260 Transformer protection RET670 2.2 ANSI
Commissioning manual

Table of Contents

Other manuals for ABB RET670

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB RET670 and is the answer not in the manual?

ABB RET670 Specifications

General IconGeneral
Rated Frequency50/60 Hz
InputsAnalog and binary inputs
ApplicationProtection of power systems
Communication ProtocolsIEC 61850, DNP3, Modbus
Operating Temperature Range-25°C to +55°C
MountingRack mounted
Number of Binary InputsUp to 48
Number of Binary Outputs32
Protection FunctionsOvercurrent Protection
OutputsBinary outputs
EnclosureIP 54
TypeLine Differential Protection
Number of Analog Inputs24

Related product manuals