INSTALLATION
INSTALLATION PROCEDURE
I-E96-192-5A 3 - 3
INSTALLATION PROCEDURE
The following steps outline the required procedure to complete
the installation of the OIC console. Follow all related safety
procedures when doing these steps.
NOTE:
Before removing the multibus keyboard module from the
multibus card cage or doing maintenance on equipment containing
static sensitive devices, read
SPECIAL HANDLING
.
1. Install the cabinet or panel. Refer to the dimension draw-
ings and instructions in the installation and setup sections
found later in this section.
2. Vibration during shipping and handling may unseat the
multibus keyboard module and connections, causing prob-
lems. Verify that the module is seated and that all terminal
block screws and stud fasteners are tight.
3. Refer to IIMKM02A MULTIBUS KEYBOARD MODULE in
Section 6 to check the jumper settings.
4. Connect OIC consoles to the OIS. Refer to the installation
and setup procedure for the OIC model being installed.
5. Verify that no power is present to the OIC when making
power wiring connections. Wire AC power according to the pro-
cedures in OIC INSTALLATION. Refer to the Site Planning
and Preparation instruction, the power requirements in
Section 1 and AC POWER WIRING GUIDELINES in this section.
NOTES:
1. Verify that the incoming voltage meets the rating on the label of
TB1 on the power entry panel and Table 1-5.
2. Make certain the OICs being installed are powered using the
same power source and ground as the OIS console. Failure to do so
may cause improper operation.
6. After completing the wiring:
•
Check that the keyboards and printers are connected to
the correct port. Refer to the appropriate wiring connec-
tions and cabling section and PERIPHERALS.
•
Ethernet network cable requires a terminator at each end
of the cable.
•
Check the AC voltage sources for proper voltage and cur-
rent values. Refer to the specifications in Section 1 and AC
test in Section 4.
•
Apply power. If problems occur, refer to Section 4 for trou-
bleshooting information.