54 Initial Operation
CFPP Process Analyzer CFPP-4.2 03/2016
Note: We recommend to have the system put into operation by BARTEC BENKE
service personnel, and to have your operators and maintenance staff instructed
and trained by BARTEC BENKE.
8.1 Putting the Analyzer into Operation
Note: Before you put the analyzer into operation, you have to refill the Chiller for
Liquids with coolant. Further information to the Chiller for Liquids you find in
the provided manual for the Chiller for Liquids.
Before putting the analyzer into operation, check the protective devices (see
chapter 10.4).
After putting the analyzer into operation and running it for approx. 2 hours, the
following maintenance tasks must be carried out:
• General visual inspection (see chapter 10.5).
• Visual inspection in the measuring unit enclosure (see chapter 10.6).
• Check liquid level in the sample container (see chapter 10.14).
• Clean the test filter (see chapter 10.13).
Note:
If the residual-current device (RCD) has triggered immediately during
commissioning follow the hints in chapter 10.7 „Checking the residual-current
device (RCD)“ on page 75
.
8.2 Flushing the Product Feed Line
Flushing removes dirt particles and air from the product feed line and is only necessary
before initial operation or after maintenance or repair work on the product feed
line.
Observe the regulations for mounting the pipe connections. Please refer to the supplied
manufacturer’s documentation.