76 Maintenance
CFPP Process Analyzer CFPP-4.2 03/2016
10.7.2 Measures in case of troubles
If the RCD has triggered immediately during commissioning, do the following steps:
1. Check whether the downstream working circuit and connected current-using
equipment are connected to earth.
2. Remove insulation faults or eventually available connections between neutral
conductor and the earth conductor on the load side.
If the above mentioned causes are impossible or if the RCD malfunctions replace the RCD.
A new RCD is available at BARTEC BENKE.
If the RCD is damaged it may not be repaired.