8 Commissioning Instructions
ATTENTION!
The control systems of BÖHNKE + PARTNER and the drive system
must not be commissioned before having fulfilled the following condi-
tions:
• The control unit has been mounted and installed according to this
manual.
• Operating and setting possibilities are all known (see user manual
bp308 ).
• The valid EMC rules (electro-magnetic compatibility) are complied
with!
• The power circuit, control circuit and safety circuit have been con-
nected and checked according to this manual (see check-list).
• Instructions that also have to be followed when commissioning the
system:
- First Travel with Emergency Controls (section Fehler: Referenz
nicht gefunden),
- First Travel with Inspection Controls (section Fehler: Referenz
nicht gefunden),
- First Travel with Normal Operation Controls (section Fehler: Ref-
erenz nicht gefunden) and
- Commissioning of the Floor selector System (section Fehler: Ref-
erenz nicht gefunden).
INFO!
You must read the supplementary instructions prior to commissioning
any specially designed systems and components.
After commissioning, the actual parameters must be documented in
the printout of the setup and service menu or an up-to-date printout
has to be saved to a storage medium (memory card, USB stick). Mal-
functions stored during commissioning (malfunction stack
memory/malfunction list) can be deleted in the sub-menu »dia-
gnostics«. If third persons have access (e.g. janitor), protect the
menus against unauthorised access by using a setup and a service
code number (minimum four digits).
CAUTION!
Prior to each travel the operator has to ascertain that neither persons
nor property are endangered.
The final inspection and approval must be carried out in compliance
with the »Technical Tips« (Section Fehler: Referenz nicht gefunden).
77