Document number: ED.03783.00.001.ENG rev 4 Page 79 of 153
To switch “hysteresis” (automatic levelling, height regulation )
off and on.
When switched on, extending and retracking of the main jacks
is synchronised.
Non-synchronous lifting can cause severe safety issues.
Therefore it is required that the levelness of the load is
checked continuously, e.g. using a theodolite.
Hazard
The levelness of the load must be checked
continuously. Neglecting this instruction can lead to
fatal accidents.
Height of the whole pile of barrels, measured from bottom level
until the top of the top barrel
Current number of barrels in the pile
Status of the communication between the laptop and the
Smartbox
Internal state; valid both for Manual and Automatic mode.
The main jacks of the units as well as the mini-jacks are operated
manually.
The sequence of lifting (lowering) and the control of the mini-jacks is
completed automatically.