4. Commissioning
4-19
Festo P.BE-SPC11-SYS-ASI-EN en 0203NH
Output bit O1 supplies a 1-signal. The drive is now ready for
operation.
When the teach pr ocedure is concluded, the SPC11 knows
the locations of the mechanical end po sitions (P.01...P.02).
Y ou can now teach manually the intermediate positions
(P.03...P.04) or trigger a positioning task to the end positions
(P.01...P.02).