CBV ADVANCED MODE FUNCTIONS FOR THE FOREMAN ONLY
4.3.2 Creating mixes
To create new recipes or edit the existing ones.
To browse through all recipes
(up to 16 recipes are processed)
Weight needed to obtain 1 cube metre of recipe
Component code
To create a new recipe
- Select a recipe (e.g. No. 2).
- Press OK
.
- Press the C
key several times to cancel the recipe name.
- Type the new recipe name (e.g. Mix2)
- Press OK
to confi rm; the cursor moves to the fi rst component. Use the arrow keys (> <) to select the
component.
- Press OK
to confi rm.
- Enter the component weight.
The weights of the components entered in the RW column must be those needed to produce 1 cube
metre of material.
The amount of additive must be expressed in litres, those needed to obtain 1 cube metre of material
- Press OK
to confi rm.
SAND MP6: hygroscopic component on which the automatic
water compensation will be performed.
The system will use the MP6 curve to calculate the moisture value.
- Press ESC
to return to the menu