3.2.2 Transporting in the boiler room
Position a fork-lift or similar lifting device at the base frame of the
boiler and transport it to the designated position.
If no lifting device of this type is available:
After removing the suction unit thread a carrying belt through the
lateral openings (1) of the base frame and lift the boiler.
Position transport rollers or similar with appropriate load-bearing
capacity under the base frame and move to the designated
position.
Set up boiler at intended location
Observe the minimum clearances in the boiler room.
3.2.3 Minimum clearances in the boiler room
Dimensions
Component
Unit
Distance
A
Minimum distance between suction cyclone and wall
inches
12
B
Maintenance range for ID fan
14
C
Front of Appliance to Combustibles
36
D
Minimum distance from side of boiler to wall
8
E
Combustibles to Flue Pipe
18
F
Ceiling to Appliance
18
G
Ceiling to Suction Cyclone
12
N O T E
Clearances may only be reduced by means approved by the regulatory authority.