Section 2: Installation Operator Manual
G1900™
© Genmega 2011 2.1
INSTALLATION
2.1 Genmega G1900™ INSTALLATION
2.1.1 UNPACKING
Ste
1
Upon receipt of your new Genmega ATM, check the box and packaging for any
damage. If you suspect any damage, mark the shipping receipt to indicate suspected
concealed damage. Do not discard the ATM packaging materials until you have
verified any shipping damage claim. Contact your distributor immediately if you see
any shipping damage. It’s also advisable to take photos of any damage.
NOTE:
You have 7 days from delivery to report any concealed damage. After 7 days
we are unable to process any shipping damage claims.
Ste
2
Verify the contents carefully with the packing list to make sure all items listed are
included per your order. Notify your distributor of any shortages.
2.1.2 PHYSICAL INSTALLATION
To install the Genmega G1900™ ATM, review the following steps:
Step 1
Place the system on a flat surface during installation. The system is top-heavy and
has a tendency to tip over. Be very careful when opening the top or bottom slide
trays or vault door prior to bolting down the ATM, it will be more likely to tip.
Step 2
Use the holes in the bottom of the vault to mark the floor or ATM location. Remove
the ATM before drilling the anchor holes. Anchors are not included with the ATM.
WARNING: Do not drill the holes through the vault. Dust from the drilling
will damage ATM components and void your warranty.
Due to variations in flooring and building codes, Genmega does not recommend a
particular size or type of anchor as each installation. Consult anchor manufacturers
instructions for proper installation. Maximum anchor diameter is ½.
Step 3
Place the G1900™ ATM on top of the anchors and tighten. Note that over-tightening
the anchors can cause the vault to go out of square and make door operation
difficult. If this occurs, back off the anchors or use leveling bolts.