6.4 - LIFTING OPERATION
• Completely retract and lower all booms into the stowed position.
• Secure both boom travel latches ( A ).
• Remove all loose materials from machine.
• Retract all outriggers cylinders to fully stowed (upright) position.
• When using a crane :
• Use only the designated crane (fork lift) pockets ( B ).
• Follow all crane operating instructions as indicated by the crane manufacturer.
• Adjust rigging to keep the machine level and to minimize the risk of damage to machine.
• When using a forklift :
• Use only the designated forklift pockets ( B ).
• Follow all forklift operating instructions as indicated by the forklift manufacturer.
• Adjust rigging to keep the machine level and to minimize the risk of damage to machine.
N.B.-:-O
NLY TRAINED AND AUTHORIZED PERSONNEL SHOULD ATTEMPT TO LIFT THE AERIAL WORK
PLATFORM
USING EITHER A CRANE OR FORKLIFT.