5.3.3 Date and Time
Procedure
Step 1 Choose System Settings > System Parameters > Time.
Step 2 Set the time zone, date, and time or click Obtain Local Time, and click Submit.
Step 3 (Optional) If the NTP server is used for time synchronization, select NTP server
sync, set NTP primary server IP, NTP backup server IP, Port number, and Sync
interval (min), and click Submit.
----End
5.3.4 Creating a Micro-module Plan View
Procedure
Step 1 Choose Home > Plan View, create a micro-module in Micro-Module View and
set the layout and device quantity based on the actual micro-module scenario.
Step 2 Drag the icons of registered devices and devices on the cabinet list to appropriate
positions in the layout to create a micro-module plan view.
----End
5.3.5 How Can I Add a UPS2000G?
Prerequisites
One end of the straight-through cable has been connected to the RS485 port on
the UPS2000G, and the other end has been connected to the COM port on the
ECC800-Pro.
Procedure
Step 1 Add a UPS2000G-L.
1. Log in to the ECC800-Pro WebUI as an administrator.
2. Add a UPS2000G-L.
Table 5-4 Adding a UPS2000G-L
Path
Parameter Setting
Choose System Settings
> Device Management
and click Add Device.
The parameters for
adding devices are
displayed.
Device attribute Select UPS from the
drop-down list box.
Device Type Select UPS2000G-L from
the drop-down list box.
Connect To Select ECC800 from the
drop-down list box.
FusionModule500 Smart Mini Data Center