Huawei FusionModule500 V100R021C10 - Commissioning the Electrode Water Sensor

Huawei FusionModule500 V100R021C10
241 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Path Parameter Setting
Device
Address
In this example, device address is set to 1.
During actual conguration, set the device
address for the T/H sensor based on the
actual situation.
3. Click Test Connect to check whether the T/H sensor connects to the ECC800-
Pro properly.
If the connection is normal, click Conrm. The connected devices are
displayed in the Number of connected devices list.
If the connection is abnormal, check whether the device is properly
connected to the ECC800-Pro, whether the device and the ECC800-Pro are
running properly, and whether the parameter settings are consistent with
the device parameters.
Step 3 Check the function of the T/H sensor.
Table 5-8 Function check
Check Method Normal Connection Status
Check the running
information about the T/H
sensor on the WebUI.
Choose Monitoring > Aisle > T/H Sensor Group
> T/H Sensor n > Running Info, and view the
current cabinet temperature and humidity.
Set T/H sensor alarm
thresholds.
Choose Monitoring > Aisle > T/H Sensor Group
> T/H Sensor n > Running Parameters and set
High temperature alarm threshold, Low
temperature alarm threshold, High humidity
alarm threshold, and Low humidity alarm
threshold as required.
NOTE
The default values of High temperature alarm
threshold, Low temperature alarm threshold, High
humidity alarm threshold, and Low humidity alarm
threshold for cold channels are 35.0°C, 5.0°C, 85.0%
RH, and 15.0% RH respectively. The default values of
High temperature alarm threshold, Low
temperature alarm threshold, High humidity alarm
threshold, and Low humidity alarm threshold for
hot channels are 45.0°C, 10.0°C, 85.0% RH, and
15.0% RH respectively. The cold and hot aisles can be
determined based on the DIP switch settings of T/H
sensors.
----End
5.3.6.3 Commissioning the Electrode Water Sensor
Prerequisites
One end of the network cable has been stripped, core wires 7 and 8 have been
connected to the cable delivered with the electrode water sensor, and the other
FusionModule500 Smart Mini Data Center
User Manual 5 Power-On Commissioning