Huawei FusionModule500 V100R021C10 - Hardware Installation

Huawei FusionModule500 V100R021C10
241 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
No. Component
(5) Lithium battery
(6) 3.5 kW integrated air conditioner
(7) Water sensor
(8) Smoke detector
(9) T/H sensor
(10) rPDU
NO TE
If the IVS, server, and LAN switch are congured, determine their installation positions
based on the site requirements.
4.1.5 Personnel Requirements
Only trained and qualied personnel who fully understand basic safety
precautions are allowed to install and operate a modular data center.
CA UTION
Huawei will not be liable for any consequence caused by the violation of this
document.
The requirements are as follows:
Customers' installation personnel must be trained by Huawei and understand
how to install and operate a modular data center.
The number of installation personnel varies based on the project progress and
installation environment. Typically, two to three persons are required.
4.2 Hardware Installation
The angle of door opening by the gas spring is 110°. Ensure that the door opening
angle is less than 110°.
4.2.1 Transportation and Unpacking
FusionModule500 Smart Mini Data Center
User Manual 4 Installation Guide
Issue 01 (2020-11-30) Copyright © Huawei Technologies Co., Ltd. 61