Figure 4-23 Installing a oating nut
Step 2 Install guide rails.
Figure 4-24 Installing guide rails
1. Place a guide rail horizontally at the installation position in the cabinet.
2. Tighten the screws to secure the guide rail.
3. Repeat the preceding steps to install the other guide rail.
Step 3 Arrange at least two people to lift the server, place the server on the guide rails,
and push it into the cabinet.
Step 4 When the two mounting ears on the server contact the mounting bars on the
rack, tighten the captive screws on the mounting ears to secure the server.
Figure 4-25 Installing a server
FusionModule500 Smart Mini Data Center
User Manual 4 Installation Guide
Issue 01 (2020-11-30) Copyright © Huawei Technologies Co., Ltd. 83