4 Connecting Monitoring Cables to Devices
Copyright © Huawei Technologies Co., Ltd.
111
Dial
Switch
Default Value
Operations
7
OFF
Not in teamwork mode: Remaining in OFF
In teamwork mode: Set toggle switch 7 on the main
control boards of the first and last smart cooling
products to ON, and toggle switch 7 on the main
control boards of the other smart cooling products to
OFF.
8
ON
Remaining in ON
Step 3 Connect the other end of the network cable to the COM port on the ECC collector.
----End
4.3.7 Connecting the UPS Monitoring Cable
4.3.7.1 Connecting the UPS2000-G Monitoring Cable (MODBUS)
Prerequisites
A network cable used for monitoring is prepared.
Procedure
Step 1 Connect one end of the network cable to the COM_1 or COM_2 port on the Modbus
expansion card of the UPS2000-G.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei iManager NetEco 6000 and is the answer not in the manual?

Huawei iManager NetEco 6000 Specifications

General IconGeneral
BrandHuawei
ModeliManager NetEco 6000
CategoryServer
LanguageEnglish

Related product manuals