iManager NetEco 6000
Device Installation and Commissioning Guide
Copyright © Huawei Technologies Co., Ltd.
Configuration Requirements
UPS working mode of the
created management
domain
Select N, N+X(X=1–N), 2N, or 2(N+1) from
the drop-down list box.
Generator for the created
management domain
Select NULL, Single Generator, or Dua
Generator from the drop-down list box.
Mains frequency of the
created management
domain
Select 50HZ or 60HZ from the drop-down list
box.
Cooling mode of the
created management
domain
Select Water Cooled Direct Expansion, Air
Cooled Direct Expansion, or Chilled-water
refrigeration from the drop-down list box.
Air supply mode of the
created management
domain
Select Vertical under-floor Air-distribution
or Horizontal displacement Air-distribution
from the drop-down list box.
Plan
Refrigeratin
g
Capacity(k
W)
Cooling power of the
created management
domain
Range: floating point number of 1-10000000
(accurate to three decimal places)
The parameters with * must be set. Other parameters are optional. The value of Planned Rack Position
cannot be changed after it is set. The number of racks cannot exceed the planned number of rack places.
Therefore, the planned number of rack places should be set to a value great enough to meet the
requirements for rack view creation.
4. Click on the toolbar.
Repeat steps Step 2.1 to Step 2.4 until the configuration is complete.
Step 3 Click on the toolbar.
----End
6.1.2 Adding a Module
You can create a modular in the equipment room, branch, root node, union box, or subnet
management domain.
Prerequisites
You have logged in to the NetEco client by web browser
You have created an equipment room or NetEco site in Data Center Planning. For
detailed operations, see Creating a Domain.