NetCol5000-A(025, 035) In-row Air Cooled Smart
Cooling Product
User Manual (600 mm)
3 Installation Guide
Copyright © Huawei Technologies Co., Ltd.
55
----End
Example
A humidifier water inlet pipe and a condensate pump drainpipe are routed from the bottom or
top. You can route the pipes based on site requirements.
When routing pipes from the top, do not route the pipes over servers. If unavoidable, take
protective measures to protect the servers from being affected by pipe leakage.
Do not remove the humidifier water inlet pipe to prevent sealing fault between water inlet
pipe and the humidifier cylinder.
The humidifier water inlet pipe is a hose installed under the humidifier. When connecting the
hose, straighten the hose and secure it with cable ties.
The top and bottom pipe routing methods are the same with that of self-drainpipes. Figure
3-30 and Figure 3-31 respectively show top and bottom pipe routing.
Figure 3-30 Routing pipes from the top
(1) Humidifier water inlet
(2) Condensate pump drainpipe

Table of Contents